Now didn't someone say yesterday that they knew someone who was were still working on the "dies" (molds). If that's the case, then, they have at a maximum 90 days to build (at a minimum) over 6,000 tops.
Now who here believes that they have even a remote chance in hell that they can average 67 perfect tops per day, starting today?
Let's say that they start making V2 tops on September 15th, they will have to crank out over 90 tops per day. Does that sound plausible?
If, as I suspect, they need a total of 12,000 tops - 3k for DMSC, 7k for FE, and 2k for tops in the wild. These numbers become much more grim.
135 tops per day, starting today, to 180 tops per day starting September 15. To meet demand for 12,000 tops!
In addition, they need probably additional man hours to replace all the dirt mountain tops (20-30 mins each to transport, remove, install, and quality check each Dirt Mountain Storage Complex inmate). Assuming 2 crews (2-4 people), 2 shifts, over 30 days starting on 1 November 2021. That would be a thru-put of 96 Broncos per day (and still end up short by 120 Broncos at the end of the month).
Folks, this is not going to happen, it just is pure BS from @Ford Motor Company. They can't even be bothered to send me an email, what makes you think that can build tops that quickly?
Now who here believes that they have even a remote chance in hell that they can average 67 perfect tops per day, starting today?
Let's say that they start making V2 tops on September 15th, they will have to crank out over 90 tops per day. Does that sound plausible?
If, as I suspect, they need a total of 12,000 tops - 3k for DMSC, 7k for FE, and 2k for tops in the wild. These numbers become much more grim.
135 tops per day, starting today, to 180 tops per day starting September 15. To meet demand for 12,000 tops!
In addition, they need probably additional man hours to replace all the dirt mountain tops (20-30 mins each to transport, remove, install, and quality check each Dirt Mountain Storage Complex inmate). Assuming 2 crews (2-4 people), 2 shifts, over 30 days starting on 1 November 2021. That would be a thru-put of 96 Broncos per day (and still end up short by 120 Broncos at the end of the month).
Folks, this is not going to happen, it just is pure BS from @Ford Motor Company. They can't even be bothered to send me an email, what makes you think that can build tops that quickly?