Hi all,

apologies if this is the wrong forum. Reading through other threads, it seems people with productions dates assigned (06/21) should have received correspondence from Ford this week. I went into my tracker and while it says ‘In production’, the ‘in production’ circle isn’t checked and I received no email from Ford. Checked with my Dealer and he says he doesn’t have information for me. I’ve read there have been several 06/21 build dates pushed back, so I wanted to see if anyone can clarify this for me. Thanks in advance.

C8D67540-69FE-4834-980E-8E0167373E85.jpeg
Sponsored

 

NotApplicable

First Edition
Well-Known Member
Joined
Jul 14, 2020
Threads
36
Messages
1,889
Reaction score
4,874
Location
USA
Vehicle(s)
BEVs
Your Bronco Model
First Edition
Status moves to "in production" ~1 week before one's scheduled build DAY, which is within 7 days after the date specified in the email you received directly from Ford (this email specified a build WEEK).

So if you had a build week of 06/21, and your build did not get pushed back, the tracker should've shown "in production" starting sometime in the 06/14-06/20 date range, and the vehicle should _complete_ production (and show a check mark) sometime in the 06/21-06/28 date range. So there are still another 4 days for a 06/21 build WEEK build to finish production and still be 100% on schedule.
 
OP
OP

Clarkberry86

First Edition
Member
First Name
Clark
Joined
Apr 15, 2021
Threads
3
Messages
6
Reaction score
15
Location
Atlanta
Vehicle(s)
Ford Bronco
Your Bronco Model
First Edition
Status moves to "in production" ~1 week before one's scheduled build DAY, which is within 7 days after the date specified in the email you received directly from Ford (this email specified a build WEEK).

So if you had a build week of 06/21, and your build did not get pushed back, the tracker should've shown "in production" starting sometime in the 06/14-06/20 date range, and the vehicle should _complete_ production (and show a check mark) sometime in the 06/21-06/28 date range. So there are still another 4 days for a 06/21 build WEEK build to finish production and still be 100% on schedule.
good info. Appreciate that!
 

Blaven

Black Diamond
Well-Known Member
Joined
Jul 20, 2020
Threads
8
Messages
895
Reaction score
1,925
Location
Pennsylvania
Vehicle(s)
2021 Bronco
Your Bronco Model
Black Diamond
Clubs
 
My build week was the week of July 19th. I was pleased to learn it was pushed up to be built next week. Not the kind of news I expect from Ford.