A Ford Michigan Assembly Plant worker once posted the following:
MAP was tooled to run 72 vehicles an hour.
The line builds Broncos and Rangers. The ratio was planed to be 9 to 6, Broncos to Rangers. That means 43 Broncos/ hr.
The plan was to run two 10hr shifts. So the math would be
43x10=430 per shift x 2 shifts = 860 per day. If they ran 5 days a week that would be 4300 per week.
If they run June through December at capacity that would be 28 weeks x 4300 = 120,000. If they ran 75% it would be around 90,000.
MAP was tooled to run 72 vehicles an hour.
The line builds Broncos and Rangers. The ratio was planed to be 9 to 6, Broncos to Rangers. That means 43 Broncos/ hr.
The plan was to run two 10hr shifts. So the math would be
43x10=430 per shift x 2 shifts = 860 per day. If they ran 5 days a week that would be 4300 per week.
If they run June through December at capacity that would be 28 weeks x 4300 = 120,000. If they ran 75% it would be around 90,000.